Doors, Sanding, Plumbing & Electrical - 27 & 28 March 2012

Its been quieter around the Firehouse this week, but by no means silent.  Brad has been working away steadily at finishing off the carpentry tasks. Today he was working on the main doors again to put the third set of hinges on them.  Will and I have also been working at the Firehouse, albeit much more slowly then the professionals could do.  Yesterday we did a lot of caulking upstairs and Pete Langille came by to hook up the in-floor heating and connect the work sink. Today, Will worked on sanding on the main floor epoxy patches.  He also made the work sink come back to life. I wish you could feel how great the building is now that it has this wonderful heat emanating from the floor, but I have no way of showing that.



Seth came by to finish connecting the hot water heater and to finish off a couple of other small electrical jobs.