30 March 2012

Main Doors and Sanding - 29 & 30 March 2012



The cane bolts went in yesterday and then today, Brad drilled the holes in the concrete floor and installed the tubes that the bolts lock into. He also installed these beautiful old-looking (reproduction) latches.


Will did lots of sanding on the main floor.  He got the stairwell, the whole eastern side sanded, the pillars and most of the beam.


Since Will had done so much sanding, I had to start catching up by doing the priming.  I managed to do the stairwell today.